Skip to content
Project HELLA Autotechnik Nova - Internal Logistics Analysis and Target-State Design

HELLA Autotechnik Nova

Internal Logistics Analysis
and Target-State Design

At the HELLA Autotechnik Nova plant in Mohelnice, we mapped material flows and operational requirements. We designed a target state for faster material flow, lower inventory and higher stock turnover.

TechOne role
Audit and design
Deliverable
Target logistics design
Environment
Manufacturing and internal logistics

Accelerate Material Flow and Reduce Production Inventory

The project at the HELLA Autotechnik Nova plant in Mohelnice aimed to improve logistics efficiency, accelerate individual steps and reduce material inventory in production.

The target design therefore had to reflect actual operations and the requirements of the people involved in material flow.

We Assessed Material Flow as One Connected System

As part of the logistics audit, we gathered operational requirements and mapped material flows and individual logistics steps.

The analysis focused on their dependencies, production inventory and the points where working practices affected flow speed and material turnover.

The Analysis Led to a New Logistics Design

The findings became the basis for a target logistics concept. It described the changes required for smoother material flow and faster progression through individual steps.

The design connected operational requirements with the goal of reducing production inventory and increasing material turnover.

A Shared Basis for the Next Logistics Changes

The deliverable brought the audit findings, operational requirements and target design together in one proposal.

We then translated selected parts of the design into technical changes.

Need to Assess Material Flow in Production?

We map logistics steps and operational requirements and prepare a target-state design.

This form is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.